Construction Updates
Station 4-13155 W Alameda Pkwy. Lakewood CO
February 2010-Construction crews are working on the electrical and plumbing within the station.
View the photos
Station 8-9095 W. Jewell Avenue Lakewood CO
February 2010-Construction crews are working on the electrical and plumbing within the station.
View the photos
Station 5-14055 W. 20th Ave Golden CO
February 2010-Final plans are currently being reviewed. The upcoming neighborhood meeting is scheduled for March.
View the photos-February, 2010
View the artist drawings-March 2010
Completed Construction Projects
New Station 10, Training Center and Training Site-Construction project completed
3535 S. Kipling Parkway, Lakewood, CO
September 2009: Photo updates View the photos
August 2009: Photo updates View the photos
July 2009: Photo updates View the photos
May 2009: Photo updates View the photos
February/March2009: Photo updates View the photos
January 2009: Photo updates View the photos
November 2008: Photo updates View the photos
October 2008: Updates. View the photos.
July 2008: The Training Center and Training Site construction has begun.
View the project.
May 28, 2008: Groundbreaking ceremony.
View the photos
Project drawings
Station 14-Construction project completed
10305 W. Chatfield Avenue, Littleton, CO
Open House-Grand Reopening, August 13, 2009
Station 07-Construction project completed
6315 Mississippi Avenue, Lakewood, CO:
May, 2008: Station 7 has its grand opening!:
View the ceremony
View Station 7's demolition
Station 10-
3301 S. Field Street Lakewood, CO:
August 1, 2007: The design for station 10 is nearly finalized. Be that as it may some future design considerations may be made due to some dialog regarding placement of our vehicles.
All Project Construction Timeline